Summer 2024 Slurry Project
Doolittle Construction will be performing preventative maintenance (slurry seal) across 162 streets within the City of Rohnert Park. Work includes street cleaning, removal and replacement of striping, crack sealing and slurry seal of the affected roadways. The contractor will be providing notices to the residents adjacent to the work prior to the start of construction. During crack seal work, there may be limited temporary lane closures with flaggers. During the slurry seal placement, the roadways will be closed to vehicular traffic for up to 6 hours.
[Street Detail Table – Please click HERE for Start and End Points]
Schedule:
- Starting July 1 through July 19, you can expect to see construction equipment removing striping, adding temporary lane markers and crack sealing.
- Starting July 22, slurry seal activities will begin. Please click HERE for the proposed construction schedule for the slurry seal work.
Project Contact:
Jason Sampietro, Public Works Associate Engineer
Phone: 707-588-2235
E-mail: [email protected]
Spring 2025 Slurry Project
Street Detail Table - Start and end points