List of Capital Improvement Projects (CIP) found in the City's budget book located here: https://www.rpcity.org/city_hall/administration/city_manager/public_information/budget

If you have any questions or concerns about construction activities, please call 707-588-3300 or email [email protected].

Snyder Lane and Keiser Avenue Traffic Signal Project No. CIP1718

LOCATION: Snyder Lane between Lawrence Jones Parkway and north of Keiser Avenue (approximately 340 feet north of Keiser Avenue centerline)

DESCRIPTION: The Project consists of construction of new water main pipe to replace old water main, new storm drain pipe, bioretention areas, planting areas, curb and gutter, new sidewalk, pedestrian access ramps, asphalt concrete paving, new traffic signal and modifications to an existing traffic signal, pavement striping and markings, restoration of surface improvements, and widening of Snyder Lane to two travel lanes in each direction.


PROJECT PHASE: Design complete. Construction to begin Summer 2025 and be completed tentatively Winter 2025.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Location Map: 
Keiser Avenue Reconstruction – Phase 3

A&B Sections Neighborhood Pavement Maintenance Project No. CIP2205

LOCATION: A&B Neighborhood Sections

DESCRIPTION: The work includes pavement rehabilitation on various streets in the A&B neighborhood sections of the City, including crack sealing, weed/vegetation abatement, digout repairs, slurry sealing, traffic striping and pavement markings.


PROJECT PHASE: Design complete. Construction to begin Summer 2025 and completed late Summer 2025.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Location Map:
A & B

Trail to Crane Creek Regional Park AND Laurel Drive and Petaluma Hill Road Sidewalks Signal Improvement, Project No. CIP0719

LOCATION: Extension of Crane Creek Trail from Copeland Creek Trail on the west end of Sonoma State University to Sonoma County Crane Creek Regional Park

DESCRIPTION: Construction of approximately 7,500 feet of new trail, new pedestrian traffic signal at Laurel Drive and Petaluma Hill Road, new 90-foot span steel pedestrian bridge, two new 14-foot span metal bridges, drainage improvements, minor structures for earth retainment and drainage, concrete abutments, concrete footings, trail signage, and new fencing.


PROJECT PHASE: Design complete. Construction to begin Summer 2025 and completed tentatively Spring 2026.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Location Map:
Trail to Crane Creek


Pump Station Admin Building Project No. CIP1807

LOCATION: 201 and 301 J. Rogers Lane

DESCRIPTION: This project is the construction of a new administration building and fenced parking lot to centralize and house all Public Works Utilities operations staff. The proposed new building will be an approximately 3,290 square-foot wood framed constructed building with baton exterior siding and a standing seam metal roof. The building interior will primarily consist of office spaces, including two large open offices with workstations, five private offices, a separate conference room that is centrally located within the building, and two single user restrooms, including one new exterior access and a shower. Supporting spaces include a small kitchenette, storage room, and utility spaces.


PROJECT PHASE: 90% Design. Construction to begin Summer 2025 and be completed tentatively Spring 2026.

PROJECT ENGINEER/MANAGER: Laura Luchini, 707-588-3308

Civic Center Drive Playground Replacement Project No. CIP2207

LOCATION: Civic Center Drive

DESCRIPTION: Replacement of the previous playground structure, pathway replacement and ADA improvements.


PROJECT PHASE: Community Services Department is conducting public outreach efforts to select the new playground. Once the playground design is selected, design is estimated to begin Summer 2025 and construction completed tentatively Spring 2026.

PROJECT ENGINEER/MANAGER: Terrie Zwillinger, 707-588-3331

Dowdell Avenue Extension Project No. CIP2020

LOCATION: "Dowdell Avenue Extension" New road to be constructed between Golf Course Drive West and Business Park Drive

DESCRIPTION: This project is to provide a new emergency vehicle access road to serve the Holiday Inn Express development proposed on Business Park Drive. Work includes a water line connection from Business Park Drive to Golf Course Drive and installation and connection of a storm drain at Golf Course Drive West. This is Phase 1 of Dowdell Avenue Extension Project, Phase 2 will eventually provide a roadway for two-way traffic between Business Park Drive and Golf Course Drive West.


PROJECT PHASE: Design complete. Construction to begin Summer 2025 and completed late Winter 2025.

PROJECT ENGINEER/MANAGER: Laura Luchini, 707-588-3308

Wet Well Lining of Pump Station Number 2 and Wilfred/Arlington Sewer Force Main Repair Project No. CIP1709

LOCATION: 201 J. Rogers Lane and intersection of Wilfred Avenue and Arlington Avenue

DESCRIPTION: Improvements to Pump Station Number 2 include a new epoxy coating system within the wet well, replacement of deteriorated pipe supports, clamps and hardware, and upgrades to the existing ventilation and electrical system within the wet well, dry well and control room. Improvements to 30" sewer force main located at Wilfred Avenue and Arlington Avenue include replacement of approximately 30 feet of existing ductile iron pipe with plastic pipe (HDPE), air vacuum assembly, and fittings.


PROJECT PHASE: Design 80% complete. Construction to begin Summer 2025 and completed tentatively late Summer 2025.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Public Safety Main Radio System/Antenna Emergency Replacement Project No. CIP2412

LOCATION: Magnolia Park, Fire Station 2, Pump Station, Public Safety Main and Sonoma Mountain Radio Tower

DESCRIPTION: This project is the replacement of the Public Safety radio system, including replacing five Dispatch radio consoles. The current consoles have reached the end of their useful life and are no longer supported. The radio antennas are being replaced with microwave dishes located on poles at Magnolia Park, Public Safety Main, Pump Station and Fire Station 2. A new microwave dish is proposed to be placed on the radio tower at Sonoma Mountain.


PROJECT PHASE: Design 80% complete. Construction to begin Summer 2025 and completed tentatively late Summer 2025.

PROJECT ENGINEER/MANAGER: Terrie Zwillinger, 707-588-3331

Public Safety Main UPS Battery Backup Replacement Project No. CIP2503

LOCATION: 500 City Center Drive

DESCRIPTION: The City's server UPS (uninterruptible power supply) batter back up has reached the end of its useful life. This project replaces the UPS batter back up system, including replacing the existing 10kVA transformer.


PROJECT PHASE: Construction completed as of March 2025.

PROJECT ENGINEER/MANAGER: Terrie Zwillinger, 707-588-3331

Magnolia Tennis Court Resurfacing and Sunrise Park Pickleball Court Reconstruction Project No. CIP2307

LOCATION: Magnolia Park, 1501 Middlebrook Way and Sunrise Park, 5301 Snyder Lane

DESCRIPTION: This project reconstructs the pickleball court surface at Sunrise Park to remedy current surface cracks, minimize future cracking and restripe the existing tennis courts to permanent pickleball courts. The project also includes crack repair, painting and striping at Magnolia Tennis Courts.


PROJECT PHASE: Design complete. Construction to begin Summer 2025 and completed tentatively Spring 2026.

PROJECT ENGINEER/MANAGER: Jason Sampietro, 707-588-2235

City Hall Building Improvements Project No. CIP2501

LOCATION: 130 Avram Avenue

DESCRIPTION: This project replaces 21 heating, ventilation and air conditioning units, the flat roof area and the indoor lighting control system, including replacement of all interior light fixtures with "smart" fixtures that individually have integral functionality to dim, use motion control to turn on or off, and be on programmed schedule.


PROJECT PHASE: Design estimated to be completed by Spring 2025. Construction to begin Summer 2025 and completed tentatively Fall 2025.

PROJECT ENGINEER/MANAGER: Terrie Zwillinger, 707-588-3331

Various Streets Preventative Maintenance Project No. CIP2508

LOCATION: Citywide

DESCRIPTION: Citywide pavement maintenance including slurry seals, cape seals, overlays, grind and overlays, curb ramp replacements, and striping updates.


PROJECT PHASE: Design in progress. Construction to being Summer 2025 and be completed Fall 2025.

PROJECT ENGINEER/MANAGER: Jason Sampietro, 707-588-2235

Southwest Boulevard Complete Streets Project No. CIP2023

LOCATION: Southwest Boulevard from Commerce Boulevard to Adrian Drive

DESCRIPTION: The Southwest Boulevard Project is a transformative project along Southwest Boulevard between the roundabout at Commerce Boulevard and just east of Adrian Drive, consisting of the following components: a protected bike  lane on the north side of Southwest Boulevard: reduction of vehicle lanes to two travel lanes (one in each direction), separated by a center median with turn pockets; a new sidewalk on the south side of Southwest Boulevard to accommodate multi-directional bicyclists and pedestrians; installation of a sidewalk on the north side of Southwest Boulevard between Adrian Drive and No Name Street; bioretention areas for storm water treatment and capture; repair and beautification of the soundwall; and installation of new street lighting.


PROJECT PHASE: Construction in progress to be completed late Spring 2025.

PROJECT ENGINEER/MANAGER: Jason Sampietro, 707-588-2235

Benicia Park Concession Building Repair Project

LOCATION: 7471 Bernice Avenue

DESCRIPTION: Arson occurred at the concession building at Benicia Park in July, 2024. The Project consists of repairing the interior of the damaged concession building, including electrical, walls, countertop and door.


PROJECT PHASE: Design in progress. Construction to begin Summer 2025 and completed tentatively Fall 2025.

PROJECT ENGINEER/MANAGER: Terrie Zwillinger, 707-588-3331

Water Meter Renovation Project No. CIP1918

LOCATION: Citywide

DESCRIPTION: Water meter technology upgrades via advanced Metering Infrastructure (AMI) to best monitor water consumption and leaks. The project includes replacement of a large percentage of older water meters throughout the City. Customers will be able to monitor water consumption online when the project is complete.


PROJECT PHASE: Design in progress.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Location Map: Citywide Project
Water Meter Renovation Project

Water Tank & Well System Seismic Retrofit Project No. CIP2017

LOCATION: Citywide

DESCRIPTION: This Project will include the design to seismically retrofit seven water tanks and six water well sites within the City, including the design for connectivity to backup generators and all required electrical and control equipment infrastructure upgrades.


PROJECT PHASE: Design in progress.

PROJECT ENGINEER/MANAGER: Julian De Anda, 707-588-3317

Location Map:
Water Tank & Well System Seismic Retrofit Project

City Building Security Access Control Replacement Project No. CIP2103

LOCATION: Five City-owned building facilities

DESCRIPTION: Upgrades to building security and access control system at five City-owned building facilities.


PROJECT PHASE: Design in progress.

PROJECT ENGINEER/MANAGER: Laura Luchini, 707-588-3308

Location Map:
City Building Security Access Control Replacement

Parks Electrical Equipment Replacement Project No. CIP2208

LOCATION: Eagle Park, 1075 Emily Avenue, and Magnolia Park, 1401 Middlebrook Way

DESCRIPTION: This Project includes replacing the aging electrical equipment at the City's Parks. Priority projects were identified by an electrical assessment conducted in 2021.


PROJECT PHASE: Design in progress.

PROJECT ENGINEER/MANAGER: Laura Luchini, 707-588-3308